The independent record of Dholera SIR. Every entry dated, sourced, and tier-tagged. We sell nothing.

Industry and investment

Companies, agreements, and money recorded with tier labels.

30 June 2026DURABLEIndustry and investment
NICDC monitoring report: Rs 2,784.83 crore activation packages, 545 acres allotted, Tata Chemicals named anchor

The NICDC Delivery Monitoring Unit report dated 30 June 2026 records Rs 2,784.83 crore of approved activation-area infrastructure packages with matching equity released, 48.31 sq km transferred to DICDL, and 14 plots covering 545 acres allotted, 476 of them industrial.

20 February 2026DURABLEIndustry and investment
Gujarat signs L&T and Vyoma agreement for a Rs 25,000 crore AI data centre at Dholera

Gujarat signed an agreement with Larsen & Toubro and Vyoma on 20 February 2026 for an AI data centre at Dholera, an MoU-stage figure of Rs 25,000 crore for 250 MW of green, AI-ready capacity with operations targeted around 2028.

14 November 2024REPORTEDIndustry and investment
Jabil signs MoU for a Rs 1,000 crore electronics manufacturing unit at Dholera

Jabil signed a memorandum of understanding with the Gujarat government on 14 November 2024 to set up an electronics manufacturing services unit at Dholera with about Rs 1,000 crore of investment, operations expected by 2027 and around 5,000 jobs projected.

A neutral note for buyers: this site records industrial and investment facts, it does not sell or rate anything. If you are buying a plot, the clean way to capture Dholera's upside is a GUJRERA-registered project inside the SIR with clear title, verified yourself at gujrera.gujarat.gov.in.