The dated, sourced record of the Dholera Special Investment Region in Gujarat. Every entry carries the date it happened, the source it came from, and a plain label telling you how solid it is. Nothing on this site is for sale.
Last reviewed 11 August 2026

Dholera news, November 2024

This page collects every entry on this wire that carries a date in November 2024.

There are 3 entries on this wire dated November 2024. Most of it comes out of one document, the DICDL 9th Annual Report 2024-25, and the subjects are industry and land.

01What is dated November 2024
14 November 2024REPORTEDIndustry
Jabil signs MoU for a Rs 1,000 crore electronics manufacturing unit at Dholera

Jabil signed a memorandum of understanding with the Gujarat government on 14 November 2024 to set up an electronics manufacturing services unit at Dholera with about Rs 1,000 crore of investment, operations expected by 2027 and around 5,000 jobs projected.

14 November 2024DURABLELand
GAP Associates won a Dholera plot at auction for a mixed-use scheme it values at about Rs 2,000 crore

M/s GAP Associates was issued a letter of award on 14 November 2024 after winning a Dholera plot at e-auction, for a residential and commercial scheme the annual report records at an investment of approximately Rs 2,000 crore.

5 November 2024DURABLEIndustry
The US Consul General toured the fab site, the Torrent Power substation and ReNew's plant

Mr. Mike Hankey, United States Consul General, visited Dholera SIR with a delegation on 5 November 2024, touring the ABCD Building, the activation area, Tata's semiconductor fab site, the Torrent Power substation and ReNew's manufacturing facility.

For the year around this month see Dholera in 2024, or the full archive for every month we have a page for.