Contracts and awards

This page lists the actual construction contracts at Dholera: who won them, on what date, for how much money, and on what basis. Almost none of this has been reported anywhere, because the awards sit inside the development company's statutory annual report rather than in press releases. A signed contract with a named contractor and a rupee figure is the hardest evidence a construction project produces.

01Contracts and awards: every entry, newest first
11 August 2026REPORTEDContracts
What DICDL had out to tender on 11 August 2026: a cleanroom, two desalination contracts and no published values

We opened the DICDL tender board on 11 August 2026 and found six live invitations, none of them awarded and none of them carrying a published estimated value.

10 November 2025DURABLEContracts
The contractor that built Dholera's main office block has five claims outstanding against DICDL

The company that built the ABCD Building, Dholera's administrative and business centre, has raised five separate claims against DICDL, and the annual report prints each of them.

10 November 2025DURABLEContracts
Dholera's water treatment plant contract was terminated in 2021 and the arbitration is still running

DICDL terminated its water treatment plant contract with M/s SPML Infra Limited on 1 January 2021 for non-fulfilment of terms, and five years later the two sides are still in arbitration with claims running in opposite directions.

7 May 2025DURABLEContracts
The Dholera food court went to SCC Infrastructure at Rs 17.47 crore, the same firm that won the hospital

DICDL awarded the food court contract to M/s SCC Infrastructure on 7 May 2025 at a total project cost of Rs 17.47 crore, the second Dholera contract recorded in the same report for that firm.

27 March 2025DURABLEContracts
An accommodation block for investors was awarded to Unique Builders at Rs 26.72 crore

DICDL awarded the contract for accommodation facilities for investors on 27 March 2025 to M/s Unique Builders at a project cost of Rs 26.72 crore, with construction starting on 24 April 2025.

27 March 2025DURABLEContracts
Dholera's tent city was handed to Kamnath Private Limited for ten years, with DICDL taking a fee rather than paying a bill

The Dholera tent city was awarded on 27 March 2025 to M/s Kamnath Private Limited on a public private partnership with a ten year operating period, and the annual report records Rs 1.55 crore of management fees receivable by DICDL rather than a construction cost paid out.