PIB Release ID 1833823: Cabinet approves Dholera airport
The founding document of the Dholera airport story, issued on 14 June 2022 when the Cabinet Committee on Economic Affairs cleared phase one.
It gives the approved cost as Rs 1,305 crore, a completion window of 48 months, operations planned from 2025-26, the shareholding of the airport company, and the passenger and cargo traffic estimates. Every later claim about when the airport would open is a revision of this release.
01The document itself
- PIB Release ID 1833823: Cabinet approves Development of New Greenfield Airport Dholera, Ahmedabad
Published by Press Information Bureau / Ministry of Civil Aviation. posted: 2022-06-14. https://www.pib.gov.in/PressReleasePage.aspx?PRID=1833823
02Entries that rest on it (2)
- 2 March 2026REPORTEDAirportThe Airports Authority invited proposals to put flying training schools at Dholera airport
- 14 June 2022DURABLEAirportThe clock on Dholera airport started in June 2022: Rs 1,305 crore, 48 months, operational from 2025-26