The Wire / Airport / 2025
Happened 23 July 2025REPORTEDPublished 11 August 2026Reviewed 11 August 2026

In July 2025 the centre said the airport would be ready by December 2025 and that there had been no extension

DeshGujarat reported on 23 July 2025 that data placed in Parliament by the Minister of State for Civil Aviation put Dholera greenfield airport on track for completion by December 2025, and that the ministry said there had been no extension to the original deadline.

Carried by credible news outlets. No official document confirms it yet.

The quoted line was that the expected date of completion of the Dholera greenfield airport project is December 2025. Twelve months later the airport was reported at about 80 percent complete after a ministerial review, with operations targeted for September or October 2026.

One thing to be careful about. We could not read the underlying parliamentary answer, because the civil aviation ministry's copies are scanned images that do not extract cleanly. So this entry is attributed to DeshGujarat's report of the answer and not to the answer itself, and it is labelled reported rather than confirmed for that reason. We are not going to write Parliament was told as though we had read the paper.

What the source itself says

DeshGujarat reported on 23 July 2025 that data placed in Parliament by the Minister of State for Civil Aviation, Murlidhar Mohol, put the Dholera greenfield airport on track for completion by December 2025, and that the ministry clarified there had been no extension to the original deadline, quoting 'expected date of completion of Dholera Greenfield Airport project is December 2025'.

Every figure on this page, with its source status. Source: DeshGujarat, 23 July 2025.
WhatFigureUnitAs ofStatus
Stated completion dateDecember 20252025-07-23TARGET
Extension grantednone, per the ministry as reported2025-07-23REPORTED
Status a year laterCross-link to our published entry rather than restating itreported about 80 percent complete after a July 2026 ministerial review2026-07-20REPORTED

Last verified: 11 August 2026. Read the status column this way. CONFIRMED means the named document states the figure. REPORTED means a credible outlet states it and no document confirms it. TARGET means somebody is aiming at it. UNKNOWN means no source we hold gives it, and we would rather leave the row empty than fill it with an estimate.

What would move this onThe September to October 2026 window, and whether a formal commissioning date is ever announced.
Where this came fromDeshGujarat, 23 July 2025

Several of these documents are large PDFs on government portals that move without notice. Where a document has no stable deep link we cite it by its number and date so it can be found again. See the source register for what each document is and what we took from it.

If one of these links has moved or we have read it wrong, write to [email protected] and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.