Happened 10 November 2025DURABLEPublished 11 August 2026Reviewed 11 August 2026

DICDL spent Rs 28.07 lakh on the Bhimnath rail line, and the accounting says who is really building it

DICDL's 2024-25 accounts record Rs 28.07 lakh spent on the Bhimnath to Dholera rail line during the year, reimbursed from the state budget through DSIRDA, with the project taken up by the zonal railways and no separate company formed for it.

Confirmed by an official document: a government release, a filing, or the company's own published statement.

The spending figure is small and the structure behind it is the point. This line is not a Dholera company project financed on the Dholera balance sheet. Western Railway is building it, the state is paying through the planning authority, and DICDL is a conduit for a modest amount of expenditure rather than the promoter. Anybody assessing who carries the risk on this line should start there.

The same report records that Western Railways began the new broad gauge line connecting Dholera SIR to the existing Ahmedabad to Bhavnagar line in early 2025, and anticipates completion by early 2027. The total project cost is not disclosed in the report, so it is unknown below.

This is a different line from the Ahmedabad to Dholera semi high-speed railway approved by the Cabinet in May 2026, which this wire covers separately.

What the source itself says

The FY2024-25 annual report records that Western Railways has begun a new broad gauge line connecting Dholera SIR to the existing Ahmedabad-Bhavnagar broad gauge line, commenced early 2025 and anticipated to be completed by early 2027. The accounts record Rs 28.07 lakh incurred on the Bhimnath Dholera rail line during FY2024-25, reimbursed from the state budget through DSIRDA, with the project taken up by the zonal railways and no new SPV formed.

Every figure on this page, with its source status. Source: DICDL 9th Annual Report 2024-25.
WhatFigureUnitAs ofStatus
DICDL expenditure in FY2024-25Printed as Rs 28.07 lakh0.2807INR crore2025-03-31CONFIRMED
Completion targetearly 20272025-11-10TARGET
Construction startearly 20252025-11-10CONFIRMED
Total project costUNKNOWNINR croreUNKNOWN

Last verified: 11 August 2026. Read the status column this way. CONFIRMED means the named document states the figure. REPORTED means a credible outlet states it and no document confirms it. TARGET means somebody is aiming at it. UNKNOWN means no source we hold gives it, and we would rather leave the row empty than fill it with an estimate.

What would move this onCompletion against the early 2027 anticipation, and any disclosure of the total cost.
Where this came fromDICDL 9th Annual Report 2024-25

Several of these documents are large PDFs on government portals that move without notice. Where a document has no stable deep link we cite it by its number and date so it can be found again. See the source register for what each document is and what we took from it.

If one of these links has moved or we have read it wrong, write to [email protected] and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.