The contractor that built Dholera's main office block has five claims outstanding against DICDL

The company that built the ABCD Building, Dholera's administrative and business centre, has raised five separate claims against DICDL, and the annual report prints each of them.

Confirmed by an official document: a government release, a filing, or the company's own published statement.

The Administration and Business Centre of Dholera was awarded on an EPC basis to M/s Cube Construction Engineering Limited at a contract amount of Rs 72,31,11,111. The five claims cover excess built-up area, a steel price difference and escalation, extra foundation cost, outstanding maintenance service bills, and recovery of the bank charges for extending the performance guarantee. The largest by a distance is the built-up area claim at Rs 20.16 crore.

The report prints the five amounts and does not print a total, so the total in the table below is our arithmetic on its figures and is labelled as such. It also does not say how the claims were resolved, or whether they have been, so the outcome is unknown.

What the source itself says

Note to the FY2024-25 financial statements: the Administration and Business Centre of Dholera (ABCD) Building was awarded on EPC basis to M/s. Cube Construction Engineering Limited with a contract amount of Rs 72,31,11,111. CCEL has raised five claims: excess built-up area Rs 20,16,11,451; steel difference and escalation Rs 1,47,87,629; extra foundation cost Rs 3,43,88,296; outstanding maintenance service bills Rs 1,65,40,483; recovery of banking charges for extending the performance bank guarantee Rs 39,44,410.

Every figure on this page, with its source status. Source: DICDL 9th Annual Report 2024-25.
WhatFigureUnitAs ofStatus
Contract amountPrinted as Rs 72,31,11,11172.3111INR crore2025-03-31CONFIRMED
Claim 1, built-up area excess20.1611INR crore2025-03-31CONFIRMED
Claim 2, steel difference and escalation1.4788INR crore2025-03-31CONFIRMED
Claim 3, extra foundation cost3.4388INR crore2025-03-31CONFIRMED
Claim 4, maintenance service bills1.654INR crore2025-03-31CONFIRMED
Claim 5, bank guarantee extension charges0.3944INR crore2025-03-31CONFIRMED
Claims total, arithmetic sum of the fiveSummed by us from the five printed claim amounts; the report does not print a total27.1272INR crore2025-03-31CONFIRMED
Outcome of the claimsUNKNOWNUNKNOWN

Last verified: 11 August 2026. Read the status column this way. CONFIRMED means the named document states the figure. REPORTED means a credible outlet states it and no document confirms it. TARGET means somebody is aiming at it. UNKNOWN means no source we hold gives it, and we would rather leave the row empty than fill it with an estimate.

What would move this onAny disclosure of settlement or arbitration in the next annual report.
Where this came fromDICDL 9th Annual Report 2024-25 (PDF p.100)

Several of these documents are large PDFs on government portals that move without notice. Where a document has no stable deep link we cite it by its number and date so it can be found again. See the source register for what each document is and what we took from it.

If one of these links has moved or we have read it wrong, write to [email protected] and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.