Happened 27 March 2025DURABLEPublished 11 August 2026Reviewed 11 August 2026

An accommodation block for investors was awarded to Unique Builders at Rs 26.72 crore

DICDL awarded the contract for accommodation facilities for investors on 27 March 2025 to M/s Unique Builders at a project cost of Rs 26.72 crore, with construction starting on 24 April 2025.

Confirmed by an official document: a government release, a filing, or the company's own published statement.

The building sits on a plot of 12,096.71 square metres with a built-up area of 4,000 square metres, on an EPC basis with M/s TPF Engineering as project management consultant. It is the sort of building an industrial region puts up early, because companies inspecting a site need somewhere to stay before there is a town.

There is a second half to this story further down the wire. Operating the same building is one of the contracts DICDL has out to tender now, more than a year after the construction contract was signed.

What the source itself says

The Accommodation Facilities for Investors construction work was awarded to M/s Unique Builders on an EPC basis, award date March 27, 2025, project cost Rs 26.72 crore, PMC M/s TPF Engineering. Plot 12,096.71 sq m, built-up 4,000 sq m. Construction started April 24, 2025.

Every figure on this page, with its source status. Source: DICDL 9th Annual Report 2024-25.
WhatFigureUnitAs ofStatus
Project cost26.72INR crore2025-03-27CONFIRMED
Plot area12,096.71sq m2025-03-31CONFIRMED
Built-up area4,000sq m2025-03-31CONFIRMED
Construction start2025-04-242025-04-24CONFIRMED

Last verified: 11 August 2026. Read the status column this way. CONFIRMED means the named document states the figure. REPORTED means a credible outlet states it and no document confirms it. TARGET means somebody is aiming at it. UNKNOWN means no source we hold gives it, and we would rather leave the row empty than fill it with an estimate.

What would move this onWho wins the operations contract for the building, which is open on the DICDL tender board.
Where this came fromDICDL 9th Annual Report 2024-25 (PDF p.25)

Several of these documents are large PDFs on government portals that move without notice. Where a document has no stable deep link we cite it by its number and date so it can be found again. See the source register for what each document is and what we took from it.

If one of these links has moved or we have read it wrong, write to [email protected] and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.