The Dholera fire station contract was awarded on an item-rate basis, not EPC

M/s Aditya Infrabuilcon Pvt. Ltd. won the Dholera fire station contract on 28 February 2025 at a project cost of Rs 20.12 crore, and the annual report records the contract as item rate rather than EPC.

Confirmed by an official document: a government release, a filing, or the company's own published statement.

An item-rate contract prices each item of work separately and pays for the quantity actually built, so the final bill moves with the measured work. An EPC contract fixes a price for the whole job up front. All the other Dholera social infrastructure contracts in the same report are EPC, and this one is not, which is the sort of detail that only appears if somebody reads the document.

The station is recorded with eleven garages on a plot of 8,793.63 square metres and a built-up area of 3,001 square metres, with M/s TPF Engineering as project management consultant. Construction started on 9 May 2025.

What the source itself says

The Fire Station construction work was awarded to M/s Aditya Infrabuilcon Pvt. Ltd. on an Item Rate contract basis, award date February 28, 2025, project cost Rs 20.12 crore. Eleven garages, plot 8,793.63 sq m, built-up 3,001 sq m, PMC M/s TPF Engineering. Construction started May 09, 2025.

Every figure on this page, with its source status. Source: DICDL 9th Annual Report 2024-25.
WhatFigureUnitAs ofStatus
Project cost20.12INR crore2025-02-28CONFIRMED
Garages11garages2025-03-31CONFIRMED
Plot area8,793.63sq m2025-03-31CONFIRMED
Built-up area3,001sq m2025-03-31CONFIRMED
Construction start2025-05-092025-05-09CONFIRMED

Last verified: 11 August 2026. Read the status column this way. CONFIRMED means the named document states the figure. REPORTED means a credible outlet states it and no document confirms it. TARGET means somebody is aiming at it. UNKNOWN means no source we hold gives it, and we would rather leave the row empty than fill it with an estimate.

Correction we made to our own dataOur own tender dataset had recorded this award as EPC. The annual report says item rate. The report wins and the dataset was corrected.
What would move this onWhether the measured final cost differs from the Rs 20.12 crore recorded at award, which is the whole point of an item-rate contract.
Where this came fromDICDL 9th Annual Report 2024-25 (PDF p.26)

Several of these documents are large PDFs on government portals that move without notice. Where a document has no stable deep link we cite it by its number and date so it can be found again. See the source register for what each document is and what we took from it.

If one of these links has moved or we have read it wrong, write to [email protected] and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.