The Dholera fire station contract was awarded on an item-rate basis, not EPC
M/s Aditya Infrabuilcon Pvt. Ltd. won the Dholera fire station contract on 28 February 2025 at a project cost of Rs 20.12 crore, and the annual report records the contract as item rate rather than EPC.
Confirmed by an official document: a government release, a filing, or the company's own published statement.
An item-rate contract prices each item of work separately and pays for the quantity actually built, so the final bill moves with the measured work. An EPC contract fixes a price for the whole job up front. All the other Dholera social infrastructure contracts in the same report are EPC, and this one is not, which is the sort of detail that only appears if somebody reads the document.
The station is recorded with eleven garages on a plot of 8,793.63 square metres and a built-up area of 3,001 square metres, with M/s TPF Engineering as project management consultant. Construction started on 9 May 2025.
The Fire Station construction work was awarded to M/s Aditya Infrabuilcon Pvt. Ltd. on an Item Rate contract basis, award date February 28, 2025, project cost Rs 20.12 crore. Eleven garages, plot 8,793.63 sq m, built-up 3,001 sq m, PMC M/s TPF Engineering. Construction started May 09, 2025.
| What | Figure | Unit | As of | Status |
|---|---|---|---|---|
| Project cost | 20.12 | INR crore | 2025-02-28 | CONFIRMED |
| Garages | 11 | garages | 2025-03-31 | CONFIRMED |
| Plot area | 8,793.63 | sq m | 2025-03-31 | CONFIRMED |
| Built-up area | 3,001 | sq m | 2025-03-31 | CONFIRMED |
| Construction start | 2025-05-09 | 2025-05-09 | CONFIRMED |
Last verified: 11 August 2026. Read the status column this way. CONFIRMED means the named document states the figure. REPORTED means a credible outlet states it and no document confirms it. TARGET means somebody is aiming at it. UNKNOWN means no source we hold gives it, and we would rather leave the row empty than fill it with an estimate.
The contractor that built Dholera's main office block has five claims outstanding against DICDL
Dholera's water treatment plant contract was terminated in 2021 and the arbitration is still running
The Dholera food court went to SCC Infrastructure at Rs 17.47 crore, the same firm that won the hospital
Everything we recorded in February 2025
Several of these documents are large PDFs on government portals that move without notice. Where a document has no stable deep link we cite it by its number and date so it can be found again. See the source register for what each document is and what we took from it.
If one of these links has moved or we have read it wrong, write to [email protected] and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.