Dholera's 200-bed hospital contract went to an SCC Infrastructure and P. R. Patel joint venture
The state company building Dholera awarded the contract for a 200-bed hospital on 16 December 2024 at a total project cost of Rs 133.68 crore, and construction started on site on 7 February 2025.
Confirmed by an official document: a government release, a filing, or the company's own published statement.
The work went to a joint venture of M/s SCC Infrastructure and M/s P. R. Patel & Co. on an EPC basis. EPC means engineering, procurement and construction, where one contractor carries both the design and the build for an agreed price rather than the client managing the two separately. The report names M/s Hites as the project management consultant. The hospital sits on a plot of 9,668 square metres with a built-up area of 15,815 square metres.
This is worth reading because a hospital is one of the things a place needs before anybody will live in it, and because the contract has not been reported anywhere. The award paragraph sits on page 22 of a 115 page statutory report on a government portal, which is the sort of document that gets published and then never opened.
The Integrated Healthcare Facility construction work was awarded to the joint venture of M/s SCC Infrastructure and M/s P. R. Patel & Co. on an EPC basis, award date December 16, 2024, total project cost Rs 133.68 crore, PMC M/s Hites. Construction started February 7, 2025 and was under way at the date of the report.
| What | Figure | Unit | As of | Status |
|---|---|---|---|---|
| Total project costThe report calls this 'total project cost', not a separately stated bid amount | 133.68 | INR crore | 2024-12-16 | CONFIRMED |
| Plot area | 9,668 | sq m | 2025-03-31 | CONFIRMED |
| Built-up area | 15,815 | sq m | 2025-03-31 | CONFIRMED |
| Beds | 200 | beds | 2025-03-31 | CONFIRMED |
| Construction start | 2025-02-07 | 2025-02-07 | CONFIRMED | |
| Contract completion dateNo source discloses a contract duration or scheduled completion | UNKNOWN | UNKNOWN |
Last verified: 11 August 2026. Read the status column this way. CONFIRMED means the named document states the figure. REPORTED means a credible outlet states it and no document confirms it. TARGET means somebody is aiming at it. UNKNOWN means no source we hold gives it, and we would rather leave the row empty than fill it with an estimate.
The contractor that built Dholera's main office block has five claims outstanding against DICDL
Dholera's water treatment plant contract was terminated in 2021 and the arbitration is still running
The Dholera food court went to SCC Infrastructure at Rs 17.47 crore, the same firm that won the hospital
Everything we recorded in December 2024
Several of these documents are large PDFs on government portals that move without notice. Where a document has no stable deep link we cite it by its number and date so it can be found again. See the source register for what each document is and what we took from it.
If one of these links has moved or we have read it wrong, write to [email protected] and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.