Dholera's integrated school was awarded to Build Well Engineers at Rs 27.99 crore
The contract for an integrated school at Dholera went to M/s Build Well Engineers on 28 February 2025 at a project cost of Rs 27.99 crore, and construction started on 13 June 2025.
Confirmed by an official document: a government release, a filing, or the company's own published statement.
The report describes a school built to CBSE and IB standards running from nursery to twelfth standard, on a plot of 34,529 square metres with a built-up area of 6,082.11 square metres. The project management consultant is M/s TPF Engineering Pvt Ltd, and the contract is on an EPC basis, meaning one contractor holds both the design and the construction.
The school, the hospital and the fire station were all awarded within roughly ten weeks of each other, which is the clearest signal in the record that DICDL moved from trunk roads and pipes to the buildings people actually use.
The Integrated School construction work was awarded to M/s Build Well Engineers on an EPC basis, award date February 28, 2025, project cost Rs 27.99 crore, PMC M/s TPF Engineering Pvt Ltd. CBSE/IB standards, nursery to 12th standard. Construction started June 13, 2025.
| What | Figure | Unit | As of | Status |
|---|---|---|---|---|
| Project cost | 27.99 | INR crore | 2025-02-28 | CONFIRMED |
| Plot area | 34,529 | sq m | 2025-03-31 | CONFIRMED |
| Built-up area | 6,082.11 | sq m | 2025-03-31 | CONFIRMED |
| Construction start | 2025-06-13 | 2025-06-13 | CONFIRMED |
Last verified: 11 August 2026. Read the status column this way. CONFIRMED means the named document states the figure. REPORTED means a credible outlet states it and no document confirms it. TARGET means somebody is aiming at it. UNKNOWN means no source we hold gives it, and we would rather leave the row empty than fill it with an estimate.
The contractor that built Dholera's main office block has five claims outstanding against DICDL
Dholera's water treatment plant contract was terminated in 2021 and the arbitration is still running
The Dholera food court went to SCC Infrastructure at Rs 17.47 crore, the same firm that won the hospital
Everything we recorded in February 2025
Several of these documents are large PDFs on government portals that move without notice. Where a document has no stable deep link we cite it by its number and date so it can be found again. See the source register for what each document is and what we took from it.
If one of these links has moved or we have read it wrong, write to [email protected] and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.