The dated, sourced record of the Dholera Special Investment Region in Gujarat. Every entry carries the date it happened, the source it came from, and a plain label telling you how solid it is. Nothing on this site is for sale.
Last reviewed 11 August 2026
The Wire / Industry / 2025
Happened 31 August 2025DURABLEPublished 11 August 2026Reviewed 11 August 2026

Between two monitoring reports, Dholera's trunk infrastructure went from nearing completion to complete

The Delivery Monitoring Unit report as at 30 June 2025 says trunk infrastructure works are nearing completion. The report as at 31 August 2025 says they are complete. No measured quantity in the reports changed alongside the wording.

Confirmed by an official document: a government release, a filing, or the company's own published statement.

Plots allotted stayed at 11 and area allotted stayed at 495 acres across the two reports. The wording then stays at complete in every subsequent report through the one as at 30 June 2026. What moved was a status word, and a status word is not a measurement, so nothing in the series tells us what was finished between the two dates.

This is the kind of change that only shows up if somebody reads the same document eight times. It matters because that one word is the basis of the claim, repeated in a parliamentary answer a month earlier and in a great deal of marketing since, that Dholera's first phase is done.

What the source itself says

The DMU report as on 30.06.2025 uses the wording 'trunk infrastructure works are nearing completion'. The report as on 31.08.2025 uses 'trunk infrastructure works are complete', and the wording stays complete through the report as on 30.06.2026. No measured quantity changed alongside it: plots allotted stayed at 11 and area at 495 acres.

Every figure on this page, with its source status. Source: NICDC/DPIIT Delivery Monitoring Unit report, as on 2025-06-30, NICDC/DPIIT Delivery Monitoring Unit report, as on 2025-08-31, NICDC/DPIIT Delivery Monitoring Unit report, as on 2026-06-30.
WhatFigureUnitAs ofStatus
Wording beforetrunk infrastructure works are nearing completion2025-06-30CONFIRMED
Wording aftertrunk infrastructure works are complete2025-08-31CONFIRMED
Plots allotted, unchanged11plots2025-08-31CONFIRMED
Any measured quantity behind the changeThe reports give a status word, not a measurementUNKNOWNUNKNOWN

Last verified: 11 August 2026. Read the status column this way. CONFIRMED means the named document states the figure. REPORTED means a credible outlet states it and no document confirms it. TARGET means somebody is aiming at it. UNKNOWN means no source we hold gives it, and we would rather leave the row empty than fill it with an estimate.

What would move this onAny measured quantity, in any government document, that supports or dates the change.
Where this came fromNICDC/DPIIT Delivery Monitoring Unit report, as on 2025-06-30 (no stable deep link; cite by document number)
NICDC/DPIIT Delivery Monitoring Unit report, as on 2025-08-31 (no stable deep link; cite by document number)
NICDC/DPIIT Delivery Monitoring Unit report, as on 2026-06-30 (no stable deep link; cite by document number)

Several of these documents are large PDFs on government portals that move without notice. Where a document has no stable deep link we cite it by its number and date so it can be found again. See the source register for what each document is and what we took from it.

If one of these links has moved or we have read it wrong, write to [email protected] and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.