The dated, sourced record of the Dholera Special Investment Region in Gujarat. Every entry carries the date it happened, the source it came from, and a plain label telling you how solid it is. Nothing on this site is for sale.
Last reviewed 11 August 2026
The Wire / Industry / 2025
Happened 16 June 2025REPORTEDPublished 11 August 2026Reviewed 11 August 2026

Fifteen hundred serviced apartments are being built for the fab's workforce, and a quarter of the first tranche was occupied

Business Standard reported on 16 June 2025, citing a report by The Economic Times, that 1,500 serviced apartments are being built at Dholera for expatriates, Tata employees and supplier network workers, with about 275 units then available and 250 of them occupied.

Carried by credible news outlets. No official document confirms it yet.

The report describes another 225 units nearing completion near the plant and work begun on a further 1,000 expected by early 2026. It also says the Tata Group received a 10 acre land allotment for its own residential development, with 530 apartments planned by mid-2027.

The occupancy number is the one that means something. Two hundred and fifty occupied units is the only figure in the public record that puts actual people living at Dholera because of the fab, rather than jobs projected for later.

This entry is second-hand and labelled accordingly. Business Standard attributes the numbers to The Economic Times, so nobody has confirmed them against a document and neither have we.

What the source itself says

Business Standard reported on 16 June 2025, citing a report by The Economic Times, that 1,500 serviced apartments are being built in Dholera for expatriates, Tata employees and supplier-network workers; about 275 units were already available with 250 occupied; another 225 were nearing completion near the plant; and work had begun on 1,000 more expected by early 2026. It also reports that the Tata Group received a 10-acre land allotment for its own residential development, planning 530 apartments by mid-2027.

Every figure on this page, with its source status. Source: Business Standard, 16 June 2025.
WhatFigureUnitAs ofStatus
Total serviced apartments planned1,500units2025-06-16REPORTED
Units available at that dateabout 275units2025-06-16REPORTED
Units occupied250units2025-06-16REPORTED
Units nearing completion225units2025-06-16REPORTED
Further units under way1,000units2025-06-16REPORTED
Tata residential allotment10acre2025-06-16REPORTED
Tata apartments plannedStated as by mid-2027530units2027-06-30TARGET

Last verified: 11 August 2026. Read the status column this way. CONFIRMED means the named document states the figure. REPORTED means a credible outlet states it and no document confirms it. TARGET means somebody is aiming at it. UNKNOWN means no source we hold gives it, and we would rather leave the row empty than fill it with an estimate.

What would move this onA first-hand source for the occupancy figures, and whether the 1,000 further units arrived by early 2026 as expected.
Where this came fromBusiness Standard, 16 June 2025

Several of these documents are large PDFs on government portals that move without notice. Where a document has no stable deep link we cite it by its number and date so it can be found again. See the source register for what each document is and what we took from it.

If one of these links has moved or we have read it wrong, write to [email protected] and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.