The dated, sourced record of the Dholera Special Investment Region in Gujarat. Every entry carries the date it happened, the source it came from, and a plain label telling you how solid it is. Nothing on this site is for sale.
Last reviewed 11 August 2026
The Wire / Contradictions / 2026
Happened 30 March 2026DURABLEPublished 11 August 2026Reviewed 11 August 2026

Two government releases give two different costs for the same expressway

The road transport ministry said on 27 February 2026 that the Ahmedabad to Dholera expressway was built at a total project cost of Rs 5,800 crore. The Prime Minister's Office said on 30 March 2026 that it was built at a cost of over Rs 5,100 crore. The two statements are 31 days and about Rs 700 crore apart.

Confirmed by an official document: a government release, a filing, or the company's own published statement.

We are not adjudicating. Both are official releases, both carry release identifiers, and both are printed below so the difference can be seen rather than smoothed over. Treat the over Rs 5,100 crore as a floor rather than a point figure, because that is how it is written.

Cost figures for large road projects legitimately differ by scope, since one may include land acquisition and another may not, and neither release states its scope. That is an explanation for how it can happen. It is not a reconciliation, and nobody has published one.

What the source itself says

PIB release 2233516 of 27 February 2026, from the Ministry of Road Transport and Highways, says the expressway was 'built at a total project cost of Rs 5,800 crore'. PIB release 2246772 of 30 March 2026, from the Prime Minister's Office, says the Prime Minister will inaugurate 'the Ahmedabad-Dholera Expressway, an access-controlled highway built at a cost of over Rs 5,100 crore'. The two figures are 31 days and Rs 700 crore apart.

Every figure on this page, with its source status. Source: PIB Release ID 2233516, 27 February 2026, PIB Release ID 2246772, 30 March 2026.
WhatFigureUnitAs ofStatus
MoRTH figure5,800INR crore2026-02-27CONFIRMED
PMO figureover 5100INR crore2026-03-30CONFIRMED
DifferenceArithmetic on the two printed figures; treat 'over 5,100' as a floor700INR crore approx2026-03-30CONFIRMED
Which figure is the final costDo not adjudicate. Print both with release IDs.UNKNOWNUNKNOWN

Last verified: 11 August 2026. Read the status column this way. CONFIRMED means the named document states the figure. REPORTED means a credible outlet states it and no document confirms it. TARGET means somebody is aiming at it. UNKNOWN means no source we hold gives it, and we would rather leave the row empty than fill it with an estimate.

What would move this onA final audited cost, most likely in a road ministry annual report or a CAG audit.
Where this came fromPIB Release ID 2233516, 27 February 2026
PIB Release ID 2246772, 30 March 2026

Several of these documents are large PDFs on government portals that move without notice. Where a document has no stable deep link we cite it by its number and date so it can be found again. See the source register for what each document is and what we took from it.

If one of these links has moved or we have read it wrong, write to [email protected] and we will fix the entry and say so on the corrections page. For how we decide what counts as confirmed, see how we source and correct. For the full dated history of the region, see the Dholera timeline. For any term above you do not recognise, see the glossary.