DICDL 9th Annual Report, financial year 2024-25
The single most useful document about Dholera that almost nobody has opened. 115 pages of statutory reporting from the company that actually builds the region, filed because company law requires it rather than because anybody wanted to publicise it. Thirty-four entries on this site come out of it.
It carries the construction contract awards with contractor names, award dates and rupee values on pages 22 to 29, the audited accounts, the notes disclosing the arbitration and the contractor claims on pages 99 to 101, the board and secretarial audit records, and the Comptroller and Auditor General's certificate.
01The document itself
- Dholera Industrial City Development Limited, 9th Annual Report 2024-25 (FY ended 31 March 2025)
Published by Dholera Industrial City Development Limited (DICDL). statutory audit report: 2025-08-22, cag nil comment certificate: 2025-10-07, agm notice signed: 2025-11-06, boards report and secretarial audit signed: 2025-11-10. 115 pages. https://dholera.gujarat.gov.in/web/document/download?model=website.documents&field=file&filename_field=Ninth%20Annual%20Report%20FY%202024-25.pdf&id=199
02Entries that rest on it (34)
- 10 November 2025DURABLEContractsThe contractor that built Dholera's main office block has five claims outstanding against DICDL
- 10 November 2025DURABLEContractsDholera's water treatment plant contract was terminated in 2021 and the arbitration is still running
- 10 November 2025DURABLEThe accountsDICDL paid no dividend again, and its exemption request from the year before is still unanswered
- 10 November 2025DURABLEThe accountsDICDL carries a Rs 318 crore liability for money the central corridor company spent on Dholera since 2008
- 10 November 2025DURABLEThe accountsCommitted but unspent capital work at Dholera rose to Rs 341 crore
- 10 November 2025DURABLEThe accountsDICDL spent Rs 44.84 lakh on corporate social responsibility and left Rs 16.50 lakh unspent
- 10 November 2025DURABLEThe accountsDholera's development company has had three managing directors since 2019 and no independent director
- 10 November 2025DURABLELandTata Chemicals dropped off Dholera's named allottee list and Inox Air Products appeared
- 10 November 2025DURABLELandGujarat's land contribution to Dholera is on the books at Rs 2,898.50 crore, and the share register is built one share to the rupee
- 10 November 2025DURABLELandHalf the land DSIRDA gave DICDL can be sold freely, and the rest is reserved by rule
- 10 November 2025DURABLEContradictionsOne government document calls Dholera's trunk infrastructure complete while another still calls it nearing completion
- 10 November 2025DURABLEContradictionsDICDL's own two annual reports describe the expressway with different lane counts
- 10 November 2025DURABLEContradictionsThe expressway's deadline moved twice in DICDL's own annual reports before the road opened
- 10 November 2025DURABLEContradictionsDholera airport's cargo operations were expected to begin in 2025 and there is no record that they did
- 10 November 2025DURABLEConnectivityDICDL spent Rs 28.07 lakh on the Bhimnath rail line, and the accounting says who is really building it
- 7 October 2025DURABLEThe accountsThe national auditor issued a nil-comment certificate on DICDL's 2024-25 accounts
- 22 August 2025DURABLEThe accountsDholera's development company swung from a Rs 44 crore loss to a Rs 52 crore profit on a third of the revenue
- 22 August 2025DURABLEThe accountsDICDL changed statutory auditor between the two annual reports
- 7 May 2025DURABLEContractsThe Dholera food court went to SCC Infrastructure at Rs 17.47 crore, the same firm that won the hospital
- 27 March 2025DURABLEContractsAn accommodation block for investors was awarded to Unique Builders at Rs 26.72 crore
- 27 March 2025DURABLEContractsDholera's tent city was handed to Kamnath Private Limited for ten years, with DICDL taking a fee rather than paying a bill
- 7 March 2025DURABLESemiconductorsMore than 170 industry visitors were taken round the Dholera fab site over two days
- 5 March 2025DURABLEIndustryThe chief minister laid the foundation stone for the hospital, school and fire station after the contracts had already been signed
- 28 February 2025DURABLEContractsDholera's integrated school was awarded to Build Well Engineers at Rs 27.99 crore
- 28 February 2025DURABLEContractsThe Dholera fire station contract was awarded on an item-rate basis, not EPC
- 4 February 2025DURABLESemiconductorsA 31 member Japanese semiconductor committee toured Dholera in February 2025
- 31 January 2025DURABLEEnergy and waterA Japanese water industry mission inspected Dholera's water and effluent plants
- 24 December 2024DURABLELandSeksaria Buildcon and The Amore Banquet won the Dholera three-star hotel plot
- 16 December 2024DURABLEContractsDholera's 200-bed hospital contract went to an SCC Infrastructure and P. R. Patel joint venture
- 14 November 2024DURABLELandGAP Associates won a Dholera plot at auction for a mixed-use scheme it values at about Rs 2,000 crore
- 5 November 2024DURABLEIndustryThe US Consul General toured the fab site, the Torrent Power substation and ReNew's plant
- 28 October 2024DURABLEPolicyThe DPIIT secretary and the NICDC chief executive toured Dholera and ReNew's plant in October 2024
- 11 September 2024DURABLESemiconductorsDICDL took Dholera to SEMICON India 2024 with the state electronics mission
- 18 April 2024DURABLEThe accountsDICDL is appealing a Rs 64.67 lakh income tax demand from 2018-19